Before After Analysis Question

Before After Analysis Question

Before After Analysis Question

Before after analysis question.

As a Process Excellence Leader you are required to validate if a six sigma project has been successful or not. What statistical test shall be used to compare the before & after of the following metric
a) Handling time mean
b) Handling time median
c) Handling time variance
d) Handling time std dev
e) Count of claims processes
f) Proportion of defects

3 THOUGHTS ON “BEFORE AFTER ANALYSIS QUESTION.”